Warning commissioning

Won't export / nuisance trips after commissioning

Symptom: New install powers up but won't export, or trips intermittently — no obvious hardware fault.

If a fresh install behaves oddly with no clear hardware fault, check the settings first.

1. Grid standard & region

  • Safety standard must be AS/NZS 4777.2 with the region that matches the DNSP. The wrong region applies the wrong voltage/frequency limits and causes “won’t export” or F13 trips.

2. Export limit

  • If the connection approval specifies an export limit (or zero-export), confirm it’s set correctly — and that the CT/meter it relies on is actually reading (see smart meter wiring).

3. Working mode

  • Confirm the working mode (self-consumption / time-of-use / zero-export) and the time periods match what the customer expects. A misconfigured schedule looks like a fault.

4. Then check the grid itself

  • Only after the settings are confirmed, measure grid voltage/frequency — long rural runs and weak streets cause genuine over-voltage trips that no setting will fix.

Re-running commission a Deye system in 5 minutes in order catches most of these. Document grid readings before escalating to the DNSP.